The cutting had to be widened without taking the carriageway out of service, so the permanent wall also had to be the temporary works. We designed a bored pile wall with two rows of ground anchors, installed in bays short enough that the slope above was never unsupported.
Ground data was thin at tender stage, so we specified three extra boreholes before detailing. They found a clay band two metres higher than assumed, which changed the anchor lengths and saved a claim later.
Movement was monitored throughout construction against limits we set in the design. Peak measured deflection at the crest was eleven millimetres, against a permitted twenty-five.