A contractor once told us, kindly, that our best drawing was the one with the fewest clever ideas on it. We took it as a compliment. The test of a reinforcement drawing is not elegance; it is whether the steel can be tied in the right order, by hand, in the rain, without a phone call.
Congestion is a design decision
Most unbuildable details are congested ones. Four layers meeting at a column head, bars at 100 centres crossing each other in two directions, a bundle that leaves no room for a poker — all of it is legal on paper and miserable on site. When a zone is tight, we would rather increase a section by 25 millimetres or move to a larger bar at wider spacing than ask a gang to perform surgery.
What we always draw out in full
- Transfer zones where columns change line
- Beam-to-column junctions with bars arriving from three directions
- Corbels, nibs and anything supporting a precast unit
- Starter bars and the sequence in which they are cast
- Openings through slabs and the trimming around them
Order of work belongs on the drawing
Reinforcement is assembled in a sequence, and the sequence is part of the design. We note which cage goes first, where laps fall and which bars must be threaded before a neighbouring cage closes the space. Where a detail depends on an order, we say so on the drawing rather than hoping someone works it out.
Then we come and look
We inspect reinforcement before every significant pour, with the drawing in hand. It is the fastest feedback a designer can get: if a detail was awkward, the fixer will say so within thirty seconds, and the next version of that detail is better. Over twenty-four years that loop has done more for our drawings than any software.
If you are pricing a frame and the details worry you, send them over. We are happy to say whether we think they can be built as drawn.